Overview of Generation Interconnections

As co-participants in the California energy market, certain Interconnection Customers (ICs) may require an interconnection with SDG&E-owned electric transmission facilities in order to transact in the energy marketplace.

Potential ICs should review the following information when applying for electrical interconnection with SDG&E-owned transmission or distribution facilities.

Before a meeting can be established with SDG&E to discuss interconnecting a potential generation project, the IC needs to enter the project into the appropriate generation interconnection process, by identifying whether the project will be interconnecting to the SDG&E Transmission System or Distribution System.

Transmission System - Connecting at 69kV and above

Distribution System - Connecting at 12.47kV and below

The IC is to complete the appropriate Interconnection Request form (IR) and provide the required study deposit for the project to enter the appropriate study queue.

SDG&E Generation Interconnection Request Queue

SDG&E WDAT Interconnection Queue
SDG&E WDAT Interconnection Queue
SDG&E WDAT & Rule 21 Interconnection Queue
SDG&E WDAT & Rule 21 Interconnection Queue

SDG&E provides non-discriminatory access to the grid for all generation projects that request interconnection to the grid under Federal Energy Regulatory Commission (FERC) regulations, the California Independent System Operator (CAISO) Tariff and the SDG&E tariff.

Interconnection Information and Map

SDG&E Transmission System Overview

The San Diego Gas & Electric’s (SDG&E) transmission system (69 kV and above) is under the operational control of the California Independent System Operator (CAISO).  Interconnection of generation facilities to the SDG&E transmission system is subject to the CAISO Federal Energy Regulatory Commission (FERC) approved Generation Interconnection Procedures (GIP) tariff.  Projects proposing to interconnect to the SDG&E transmission system (transmission lines and transmission substations) are studied in a cluster.  In order to evaluate the feasibility of an individual project, as far as transmission capacity is concerned, all projects in that cluster need to be considered to identify the available capacity. 

The transmission system included in the map on this web site provides the transmission information regarding the outlet capability from the distribution substation by indicating how the distribution substation/system is integrated into the transmission network.  This provides interconnecting customers information regarding the power flow capability from the distribution substation onto the transmission system.

SDG&E’s transmission system, and generally the larger CAISO managed transmission grid, is configured as a network electrical system. The nature of a network transmission system is such that it requires a specific suite of studies to identify the available capacity on any transmission or substation within the network.  The networked characteristic of the transmission system serves in providing flexibility, unlike a radial system (distribution), in redistributing the power flow when an element of the network is out of service for maintenance or is forced out.

Interconnection interactive map

Interconnection Handbook