Yêu cầu đề xuất về độ tin cậy giai đoạn 2027-2032
San Diego Gas & Electric Company (“SDG&E”)’s 2027 – 2032 Reliability Request for Offers (“RFO”) seeks offers for (i) Mid-Term Reliability (“MTR”) Resource Adequacy (“RA”) capacity to come online by and between June 1, 2027, and June 1, 2028, as required by the California Public Utilities Commission ("CPUC") Decision (“D.”) 21-06-035, D.23-02-040 and D.24-02-047 (together, the “Decisions”), and (ii) additional generic capacity in response to potential procurement targets under CPUC Rulemaking 25-06-019 to come online by and between June 1, 2027 and June 1, 2032. SDG&E is soliciting resources including energy storage systems (“ESS”) and California Renewable Portfolio Standard (“RPS”)-eligible renewable generation hybrid and co-located energy storage systems. All contracts shall have a minimum duration of 10 years.
Trang web này cung cấp tổng quan về việc chào mời tham gia thị trường. Người tham gia được khuyến khích mạnh mẽ tải xuống tài liệu. Quy trình RFO và các tài liệu liên quan Thông tin chi tiết về loại tài nguyên quan tâm, được trình bày bên dưới, sẽ giúp bạn hiểu rõ mọi khía cạnh của yêu cầu đề xuất này.
Tin tức & Cập nhật mới nhất
- RFO launched November 24, 2025
- RFO Reopened February 13, 2026
Sản phẩm được yêu cầu & Tài liệu nộp kèm
The Decisions require, among other things, SDG&E to procure a total of 619.5 megawatts (“MWs”) of net qualifying capacity (“NQC”), set forth in more detail in the categories set forth in Table 1, below.
|
Type of Resource |
2023 |
2024 |
2025 |
2026 |
2027 |
2028 |
Tổng cộng |
|
Firm zero-emitting resources* |
- |
- |
- |
- |
- |
41.4 |
41.4 |
|
Long-duration storage resources |
- |
- |
- |
- |
- |
41.4 |
41.4 |
|
Any other type of non- fossil-fueled resource |
82.7 |
247.6 |
62.3 |
72.0 |
72.0 |
82.7 |
536.6 |
|
Tổng cộng |
82.7 |
247.6 |
62.3 |
72.0 |
72.0 |
82.9 |
619.5 |
|
Zero-emitting resources required by no later than 2025 |
- |
- |
103.1 |
- |
- |
- |
103.1 |
* The LLT resource requirements are equally divided among long-duration storage and firm, zero-emitting generation resources.
SDG&E has a preference for projects at or around the NQC of the above targets, but will accept and consider offers for larger projects pursuant to the evaluation process described below.
Table 3, below, shows the Commission approved incremental effective load carrying capacity (“ELCC”) values that will be applied to resources’ nameplate capacities to calculate the NQC for offers intended to count towards SDG&E’s MTR requirements shown in Table 1 above. September NQC was determined by utilizing the Incremental ELCC Study for Mid-term Reliability Procurement by E3 and Astrape and updated in January 2023, at https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/integrated-resource-plan-and-long-term-procurement-plan-irp-ltpp/20230210_irp_e3_astrape_updated_incremental_elcc_study.pdf.
Table 3: Resource ELCC Values by Year
|
Incremental ELCCs |
2023 |
2024 |
2025 |
2026 |
2027 |
2028 |
|
4-hr battery |
96.3% |
90.7% |
75.1% |
76.6% |
74.0% |
76.5% |
|
5-hr battery |
97.2% |
92.1% |
77.4% |
78.5% |
77.3% |
79.9% |
|
6-hr battery |
98.0% |
93.4% |
79.6% |
80.3% |
80.5% |
83.3% |
|
8-hr battery |
98.2% |
94.3% |
84.0% |
84.0% |
87.1% |
90.1% |
|
Năng lượng mặt trời |
7.8% |
6.6% |
6.6% |
7.0% |
7.5% |
8.8% |
|
Hybrid 4-hr battery + Solar |
4-hr battery ELCC x battery nameplate + Solar ELCC x Solar nameplate |
Lịch trình RFO
The following are the key deadlines that apply to this RFO. SDG&E có quyền sửa đổi lịch trình này bất cứ lúc nào và theo quyết định riêng của SDG&E.. Respondents are responsible for accessing the RFO website for updated schedules and possible amendments to the RFO or the solicitation process.
|
* Negotiation time will vary depending on proposal specifics, including proposed contract modifications. CPUC filing requirements may also affect negotiation milestones.
Gửi đề xuất
Proposals must be submitted via PowerAdvocate in accordance with the instructions contained in the RFP Protocols. Respondents intending to bid but who do not yet have an existing account with PowerAdvocate® must first register to create a username/password to receive access to the event (event code 238300). Users with an existing PowerAdvocate® account may request access using:
https://www.poweradvocate.com/pR.do?okey=238300&pubEvent=true
Participation in this RFO requires the completion of the Offer Form, credit application, and other documents pertaining to the technology types listed below. These documents are available via the links below. Failure to provide the listed information may result in an offer being deemed non-conforming and thus may disqualify the offer from further consideration.