As co-participants in the California energy market, certain Interconnection Customers (ICs) may require an interconnection with SDG&E-owned electric transmission facilities in order to transact in the energy marketplace.
Potential ICs should review the following information when applying for electrical interconnection with SDG&E-owned transmission or distribution facilities.
Before a meeting can be established with SDG&E to discuss interconnecting a potential generation project, the IC needs to enter the project into the appropriate generation interconnection process, by identifying whether the project will be interconnecting to the SDG&E Transmission System or Distribution System.
Transmission System - Connecting at 69kV and above
CAISO Generator Interconnection Procedure (GIP)
Large Projects greater than 20MW (2 studies)
Small Projects Less than or equal to 20MW (2 studies)
Distribution System - Connecting at 12.47kV and below
WDAT Large Generator Interconnection Procedures (LGIP)
Large Projects greater than 20MW
WDAT Small Generator Interconnection Procedures
Small Projects less than or equal to 20MW and greater than 1.5MW
SDG&E Rule 21
The IC is to complete the appropriate Interconnection Request form (IR) and provide the required study deposit for the project to enter the appropriate study queue.
SDG&E provides non-discriminatory access to the grid for all generation projects that request interconnection to the grid under Federal Energy Regulatory Commission (FERC) regulations, the California Independent System Operator (CAISO) Tariff and the SDG&E tariff.
SDG&E and San Diego Gas & Electric are registered trademarks of San Diego Gas & Electric Company.
© 1998-2013 San Diego Gas & Electric Company. The Trademarks used herein are the property of their respective owners. All rights reserved.